PostPosted: Thu May 20, 2010 7:49 am 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
After months of planning, things are really happening. I'm building my studio, mostly because me (and my wife) both have music as our main hobby. We need a solid room that properly soundproofed. For the control I will be converting the garage, and for my live room I will need to build a new building. As you can see in the photos I allready have most of my insulation ( 140 m2 / 70 packs (40 kilo!! each). Today I started moving them to my messy shed, where I will stock them, I now have 26 done, once I get all 70 into place I can start working on converting my garage to my control room. Next week the first groundwork will start for the foundation of the live room. There will be 2 buildings instead of 1, because of building licences...blablabla...sucks but it will work through video / tv connection. Anyhow enough with the jibajaba..here are the pics and more info:

First my shed packed with 26 packs of insulation allready:
Image

Control room dimension: 3.5 x 5 meter = 17.5 m2 ( height is 2.70 )
Here is the before pic, and what it should get to. In the 3D model you see a the backwall will be actually extended to the backwall.
Image
Image
Image
Image
Image

Overview of the garden, there will be a 10 meter walk between the control & live room.
Live room dimensions: 4.5 x 6.5 meter = 29,25 m2 ( height: 3 meter )
Image
Image

Sketchup crashed just after exporting this, so I'm stuck and can't export the views from inside, hopefully tomorrow from work:
Image

I've allready got a curious neighboor:
Image

Another view of the currently still fully stock garage ( another 44 packs of insulation & 40 sheets of 20mm MDF to move to my shed...pfff )..
Image

Once I have the foundation ready / walls up and main construction finished I will tidy up the garden, till then, it will get messy anyway!

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Sun May 23, 2010 1:14 pm 
Offline
Site Admin
User avatar

Joined: Mon Jan 27, 2003 12:46 pm
Posts: 5259
Location: Australia
pleased to see you are finally underway :thu:


Top
 Profile  
 
PostPosted: Thu May 27, 2010 7:15 am 
Offline
Site Admin
User avatar

Joined: Thu Aug 21, 2008 10:17 am
Posts: 6182
Location: Santiago, Chile
Progress! Good news!

And I'm wondering if your curious neighbor would look good on the dinner table... :)

- Stuart -

_________________
I want this studio to amaze people. "That'll do" doesn't amaze people.


Top
 Profile  
 
PostPosted: Thu May 27, 2010 9:04 am 
Offline
Site Admin
User avatar

Joined: Mon Jan 27, 2003 12:46 pm
Posts: 5259
Location: Australia
Peking duck :thu:


Top
 Profile  
 
PostPosted: Fri May 28, 2010 12:32 am 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
Hahaha :) I bet he will! There are about 15 of those neighbours! But instead of that I can get peking duck just 500 meter further at a chinese restaurant :D...

As for progress. Had talks with a couple of guys who could dig the hole for me, but pffff most we're way to expensive. Unbelievable!
Some guys dared to charge me up to 1500 euro just to dig a hole and fill it with sand.
Anyhow, this morning I got two guys who will do it for 500 euro. The job is planned for next week thursday.
Then I have a whole week to prepare everything for the concrete slab.

Due to the fact that the first meter is in my ground is peat, I will need to dig 1 meter deep holes (where the actual "hard sand" start) of 25cm diameter. Do that every meter around, and put reinforced concrete in those columns. So I've got some preperations ahead of me! The concrete should be coming 2nd week of June...

Other option was to complete dig out a hole of 7 x 5 x 1 (deep) meter, and fill that with sand. But according to local contractors, these columns should work, and it will be sufficient enough.

This saturday I'm starting with the control room. Cleaning the space and preparing it for framing.

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Sun May 30, 2010 6:26 am 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
So.....update...
Been working hard today, most of the stuff is garden work and cleaning the "garage" to get things going in there.
First let's start with some photos:

I needed to move still another 40 packs of insulation and 40 MDF sheets out of here:
Image

No, where has that stuff gone?
Image
Image
Image

So the place is no free of all the big packs & stuff, this week I'll be focusing on getting everything from the inside stripped:
Image

The first things I need to do after I've completelly stripped everything inside is:
- Remove the doors & replace it with a new wall
- Replacing the window, once I have that done I have a great view on the garden while mixing and being busy
- Removing the beams accross, they do not carry anything or hold anything up. I only need to get claws first to fix the roof to the walls first
- Filling up some holes with concrete
- Level the floor
- Redoing the roof with new tiles
- So...greatttttttt..lot's of work to do before actually starting :)

Image

And finally some shots of what's supposed to happen to the actual live room I'm creating:
3 of the 2 walls are "inside out", all walls aren't parallel
Image
Image
Image
Image

Anyhow...done a shitload of work today, tired...and still got a lot of work to do! But I'm looking forward to it....

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Tue Aug 10, 2010 12:40 am 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
So...it is about time for an update. I had two months of really bad luck (construction wise). Eventually just before the holidays someone who takes care of the building permits came by and roasted my whole plan because of space issues.. Yes I have a garden of 700 square meters, and actually a total including my house of 1050 square meters, so you can see...a 30 square meter brick building can't fit in that garden :roll:.

Anyhow, leaving that dissapointment I first thought I'd just do the garden and check out my other options, so my garden now sort of looks like this:
Image

I still prepared everything for a concrete slab of 30 square meter tho. I actually got a permit for this tho:
Image

Ok, it isn't the ultimate, it isn't perfect (yet), but with still being 30 square meters ( 5 x 6 meters ) and a canopy roof of 2.5 meters deep I think I still can create something beautifull. The biggest disadvantage is actually the side walls ( 2,10 meter ) where as the heighest point is 3 meters. In the past I have recorded in these kind of houses, only smaller ( 3x4 ), and to be honest the slanted roof really made the drums more alive. So in the next days I'll come back and ask for some construction advices that I haven't completelly figured out yet.

The house should arrive here in 2 weeks on monday, and concrete slab will be poured now next week. Everything has been preperated it's just waiting.

Since I've ordered the house I really had to wait and keep myself busy, so I thought I put a new path on the side of my house, it really was my first time, and I feel very satisfied with the result. (photos are still from the work in progress)
Image
Image

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Tue Aug 10, 2010 6:31 pm 
Offline
Site Admin
User avatar

Joined: Mon Jan 27, 2003 12:46 pm
Posts: 5259
Location: Australia
Mate - you've been on this site for two years now - do you really think you are contributing to this site by posting meaningless pictures that just add to the cost of the data??

_________________
John Sayers Productions
The Recording Manual
Studios Under Construction


Top
 Profile  
 
PostPosted: Tue Aug 10, 2010 10:56 pm 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
I've got the pictures stored on my own website, and just linked them, if you prefer I'll delete/amend the post.

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Wed Aug 25, 2010 5:37 am 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
Finally progresssssss :yahoo:

Anyhow, yesterday I've been busy preparing everything for the concrete. I think the pictures speak for itself, the concrete is coming tuesday. The house come later that week, and I'll be ready to start building it on 11th september. Luckily I'll have plenty of help coming that day and some days after that.

First offcourse making sure everything was leveled:
Image

And the finished product:
Image

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Wed Sep 01, 2010 7:14 pm 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
Update time. Yesterday (31st august) it was finally time to poor the concrete.
First of, I owe a lot to this guy, Frank, helping me out so far. While his wife is one the verge of delivering a baby, he spend 2 evenings with me tot prepare the concrete casket, and after polishing/buffing the concrete floor.
Image

So here's the pics of yesterday:

This thing just hung over my head out of nothing:
Image

Ow...forgot it was attached to this:
Image

Then I made a very quick shot before running to the hose and guiding the concrete into it's place (yes that's my finger):
Image

Everything has been pored, vibrated and made it as flat as humanly possible, for me:
Image

This morning, after polishing:
Image
Image

Now I seriously hope they will be quick with delivery of the shed, since the weather is getting worse; more rain, wind and colder.

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Mon Sep 13, 2010 6:53 pm 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
So, in wait off the shed and delivery I thought I'd keep myself busy with a desk design!
I've allready started work on this, and bought the first materials.
I'm only really worried about the design.

If you check out the design underneath you see it's slanted a bit at the back of the rack modules. I'm worried there will be comb filtering in my mix seat. Anybody got any ideas..or shouldn't this be much of a problem?

Image
Image
Image
Image

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Tue Sep 14, 2010 3:49 am 
Offline
Senior Member
User avatar

Joined: Sat Nov 19, 2005 2:30 am
Posts: 344
Location: Gresham OR
Congrats on the pour :yahoo:
Peace
Tom

_________________
_____________________________
http://www.lost-studios.com
facebook.com/loststudiospdx


Top
 Profile  
 
PostPosted: Sat Oct 09, 2010 4:21 am 
Offline
User avatar

Joined: Fri Feb 22, 2008 10:36 am
Posts: 101
Location: Nieuw-Buinen, The Netherlands
Progress.. yesterday (thursday 7th october) the "shed" was delivered...finally. It was delayed by 10 weeks. Positive thing is I got a small discount.

Anyhow, here is how it looks now:
Image
Image

To get a good overview, I finished live room part of the studio in sketchup.
The outer size = 5.8 m x 4.8 meter. The control room will be attached in the front, thiswill be a size of 3 x 5.8 meter. But for now I will first focus on the live room.
The roof of the control room will be immediatelly there tho!
Image
Image
Image
Image

This is the plan, from out to in:
44MM pine | 12.5MM Gypsum | insulation 140kg/m3 | AIR GAP | 12.5MM Gypsum | 15MM MDF | 12.5MM Gypsum | insulation 140kg/m3
Image

Top view:
Image

And some nice renders:
Image
Image
Image
Image

Upcoming weeks I will deffinatelly have more update pics since finally I can really start now

_________________
http://www.myspace.com/samuelstudiosnl
Facebook Page


Top
 Profile  
 
PostPosted: Sat Oct 09, 2010 5:15 am 
Offline
Site Admin
User avatar

Joined: Thu Aug 21, 2008 10:17 am
Posts: 6182
Location: Santiago, Chile
There seems to be some errors in your materials list. It says:

Quote:
insulation 140kg/m3
:shock: :!: :?:

That is WAY too dense! Depending on what it is (fiberglass or mineral wool), you want something in the range of around 30 to 50 kg/m3. If you go to densities much higher than that you start to loose effectiveness for low frequencies. Yours is about 300% to 400% too dense. You should fix that.

Also, it says:

Quote:
12.5MM Gypsum | 15MM MDF | 12.5MM Gypsum
That gypsum is too thin. Too flexible, resonant frequency too high, etc. Use only 5/8" (16mm).

Also, the MDF is fine if you really want it, but it would probably be better to have it up against the studs, then put your drywall on top of that. There are two reasons why you might want MDF there: one is to give you a nailing surface across the entire wall instead of just on the studs, and the other is to give you better structural integrity (sheer). Both of those reasons imply that the wood should be on the studs, not separated from them by a sheet of drywall.

Finally, I'm curious about the orientation of your ceiling joists / rafters / whatever: they seem to be running the wrong way! They seem to be spanning the length of the building from end to end, rather than across the width, from ridge board to top plate, which is they way I've always seen it done. I'm not sure if it is OK to do it that way. Brien can probably comment on that, but for some reason it just doesn't look right to me.


- Stuart -

_________________
I want this studio to amaze people. "That'll do" doesn't amaze people.


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 74 posts ]  Go to page 1, 2, 3, 4, 5  Next

All times are UTC + 10 hours


Who is online

Users browsing this forum: Bing [Bot] and 4 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Group